Summary
Unexpected pavement cracking on eastbound Portola Avenue near Tranquility Circle needs $400,000 in extra repairs, funded by shifting county Measure BB street money from another project. Residents who drive that corridor should see smoother roads.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Impact analysis
$400,000 shifted from the Stanley/Isabel connector ramp project; change order allowance rises to $682,577.
Drivers on Portola Avenue and the Shea Sage frontage get repaired pavement.
The Stanley Boulevard/Isabel Avenue connector ramp crossing project loses $400,000, potentially delaying it.